Project Management Services

Location Sheikh Zayed Road
Project Profile B+G+M+2Serv+52Typ+R Tower Building
  G+7 Car Parking Building
Overall Project Progress 99%
Expected Handover Date End of July 2013
Update - Substantial completion of works has been acheived
  - Testing & Commissioning of all equipments is underway
  - Awaiting DEWA release of power
Location Sheikh Zayed Road
Project Profile 2B+G+M+3MECH+70 Tower Building
  G+12 Car Parking Building
Tower Building
Actual Project Duration
(as per Contract)
13 Months
Time Elapsed 9 months
Time Remaining 4 months
Planned Progress 85%
Actual Progress 80%
Delay 5%
Car Parking Building
Actual Project Duration
(as per Contract)
19 Months
(from Aug 2010)
Accelerated Completion Date May 2013
Time Elapsed 10 months
Time Remaining 4 months
Planned Progress 53%
Actual Progress 50%
Delay 3%
Expected Handover Date End of September 2013